Client:AWH Pty Ltd

Construction Period: May- June 2013

Total Value: $1 million + GST

AWH Pty Ltd required the construction of a 7,000 m2 container hardstand area at the west end of the South Store located off Sudlow Road, Bibra Lake. These works included:

  • Site clearing and topsoil stripping;
  • Installation of storm water drainage pipes and pits;
  • Construction of a 1200m3 soakage basin with surrounding 1 metre high retaining wall and safety fence – including 12no. 1800dia x 2400 deep soakwells;
  • Trenching and backfilling for provisional electrical conduits/cables and water lines;
  • Profiling of an existing section of roadway and stockpiling for use in construction of the new hardstand;
  • Construction of container hardstand pavement – subgrade, subbase, basecourse;
  • Limestone block kerbs and extruded concrete kerbs; and
  • Asphalt resurfacing of remainder of a north/south roadway.

 

This project was completed on budget and to schedule.