Client: Water Corporation

Construction Period: July – August 2007

Total Value: $330,000 + GST

The Works comprised of the roof replacement of a 1000ML Water Tank at the Brunswick Junction as follows:

  • Survey of tank to be roofed;
  • Demolition and removal of the existing steel roof and ladder;
  • Installation of precast concrete footings and columns;
  • Replacement with a steel framed and steel clad roof, including access ladders and hatches;
  • Ancillary works included providing FRP grilles over the inlet/outlet bellmouth in the tank floors; and
  • Installation of a handrail around the tank perimeter.

This project was completed on budget and to schedule.