Client: Red Gull

Construction Period: July – August 2010

Total Value: $300,000 + GST

The Works comprised of the construction of a right turn pocket, cross over and widening of Lakes Road as follows:

  • Excavation and installation of pavement materials;
  • Drainage works including installation of soakwells and side entry pits;
  • Asphalt and primerseal works;
  • Linemarking;
  • Installation of kerbing and footpath; and
  • Traffic management.

This project was completed on budget and to schedule.