Client: City of Rockingham

Construction Period: June 2018 – July 2018

Total Value: $44,000 + GST

Advanteering completed these works for the City of Rockingham in July 2018. The project was to supply and install a Fibreglass Reinforced Plastic (FRP) staircase on the Shoalwater foreshore.

The project included:

  • Earthworks
  • Construction of concrete foundations
  • Supply and install of FRP staircase
  • Landscaping to create a natural finish around the stairs

The project was effectively managed without environmental incident.