Client:Transfield Services

Construction Period: Sept – Dec 2013

Total Value: $900,000 + GST

The scope of the work involved the expansion of the north east car park at the Hillary’s Boat Harbour by 74 bays. The work generally included the following:

  • Removal of sections of existing landscaping, fencing and shared use path.
  • Construction of pavement for an additional row of 74 car parking bays.
  • Supply and installation of a storm water retention system (see photo).
  • Landscaping and vegetation reinstatement.
  • Construction of principal shared path (PSP) on new alignment.
  • Install security lighting.
  • Relocation of proposed services as specified.
  • New kerbing, parking islands and traffic calming devices.
  • Associated line marking and signage.

The project was completed on budget and ahead of schedule.